03/09/2026
In June 2022, ready-mix concrete was delivered and poured into the basement walls, ground floor columns, and ground floor slab of the Greenside Building — a nine-storey office development on Cuffe Street in Dublin, overlooking St. Stephen's Green and expected to be worth around €50 million on completion.
When testing was carried out, the concrete failed to achieve the required compressive strengths. The developer, KC Capital Property Group, terminated the contract with the main contractor and appointed a replacement. The defective concrete was removed entirely — a process that cost a minimum of €9 million in remediation alone, with total losses and damages claimed at €13 million in the High Court action that followed.
By early 2026, the case had become so financially damaging that KC Capital sought examinership, arguing that the €13 million it hoped to recover from concrete supplier Keegan Quarries was central to the company's future. The case is still before the courts.
The critical question in a dispute like this is straightforward: what actually happened between the plant and the pour? Was the mix understrength when it left the batching plant? Was anything added or altered on site? How long did it sit in the drum before it was poured? Without a locked, time-stamped, independently verifiable record of the entire delivery chain, these questions become impossibly difficult to answer — and the legal costs of trying to answer them run into the millions.
From the €13m Greenside Building dispute to Ireland's defective block crisis — real cases that show why accountability in ready-mix concrete delivery has never mattered more.