iCobus: ICT, Telecoms & Cabling

iCobus: ICT, Telecoms & Cabling iCobus is an ICT, Telecoms & Network Cabling company with offices in London and Cape Town, providing Skilled Labour Solutions.

iCobus is an ICT, Telecoms & Data Cabling Recruitment & data cabling contracting company based in London, offering labour solutions across the UK. We specialise in providing temporary, contract & permanent staff to the telecoms & data cabling industry. We offer a cost effective labour solution, by providing staff on a project specific basis and allowing our clients to grow their business and take on more projects, whilst eliminating staff overheads during quiet times.

05/11/2026

When people talk about European data centres, they usually mean five cities. Frankfurt, London, Amsterdam, Paris, Dublin.

The next tier is growing up fast.

According to JLL's mid-2026 figures, Milan now has 230 MW of live colocation capacity. Madrid and Oslo have 165 MW each, Warsaw 150 MW, Copenhagen 142 MW, Berlin 140 MW and Stockholm 91 MW.

JLL expects Milan, Iberia and the Nordics to be treated as tier-one markets within the next cycle. CBRE reports that most of the capacity contracted by AI-focused providers so far is in the Nordics, where renewable power is more available.

For engineers, that is a wider map of where the work is. For anyone planning programmes, it is more markets to resource at the same time.

The full picture is in our Outlook report. Link in the comments. 👇

30/10/2026

Last time's chart showed the big five hubs doubling. This one shows where the next wave is going.

In Q2 2026, 63% of the new data centre supply delivered across Europe was outside Frankfurt, London, Amsterdam, Paris and Dublin, according to CBRE.

The sites are moving further out too. JLL puts the average distance of hyperscale sites from a hub city at 46 km for projects delivered between 2022 and 2025. For the 2026 to 2028 pipeline, it is 175 km. Greenfield land rises from 8% to 39% of new supply.

The reason is power. Grid connection queues in the core markets stretch beyond 2030, so capacity is following the places where power can be secured.

For anyone planning delivery, that means more projects on remote sites, in more countries at once.

Full breakdown in our Outlook report. Link in the comments. 👇

28/10/2026

Europe's five biggest data centre hubs have more than doubled their live capacity since 2019.

Frankfurt, London, Amsterdam, Paris and Dublin went from about 1.8 GW of live colocation capacity to 3.8 GW by the middle of 2026, according to JLL's latest EMEA report.

A few things the race shows:
London passed 1 GW in 2024 and is still the largest market, at 1,277 MW.
Frankfurt overtook Amsterdam in 2021 and delivered a record 135 MW of new supply in 2025.
Paris delivered 72.5 MW in the first half of 2026 alone, and has just edged past Amsterdam.

We first ran this chart last year using estimates for 2024 and 2025. The figures here are restated with JLL's mid-2026 data.

The bigger story is what comes next. 1.4 GW is under construction in these five markets, and more of Europe's new supply is now landing outside them altogether.

We have pulled the data into our European Data Centre Delivery Outlook 2026 to 2028. Download link in the comments.

23/10/2026

Cabling problems rarely announce themselves. They show up as friction.

A new desk that takes a day because someone has to trace the cable first. A tray nobody will add to because it is already full. Runs in the ceiling that belonged to the last tenant, still there because nobody is sure what they do.

Individually, none of this looks urgent. Together, it is the reason upgrades overrun and simple changes cost more than they should.

Five signs it may be time to find out what is actually installed. 👇

21/10/2026

Every office has a layer of infrastructure that almost nobody in the business has seen.

Above the ceiling tiles, under the floor and up the risers sits the cabling every device, phone, camera and access point depends on. In most buildings it has been added to for years, by different contractors, for different tenants, to different standards.

None of that is visible while things work.

It shows up in moves and changes that take days instead of hours, because someone has to trace and test before they can touch anything. In outages caused by disconnecting the wrong link. In upgrade projects that overrun because the real survey happens during the work.

And in redundant cable nobody removed, because nobody could say which runs were safe to cut.

An audit will not make any of this glamorous. It turns an unknown into something you can plan around, and it usually pays for itself the first time a project does not have to start with guesswork.

The full article covers what an audit finds and how to scope one. Link in the comments. 👇

Power over Ethernet has quietly changed what a good copper installation looks like.When a cable only carried data, a big...
16/10/2026

Power over Ethernet has quietly changed what a good copper installation looks like.

When a cable only carried data, a big tidy bundle was a good bundle. Now the same cable might be powering an access point, a camera or a lighting controller, and IEEE 802.3bt allows up to 90W at the switch.

Power in a cable produces heat. Pack enough powered cables tightly together, in an enclosed space, and the temperature inside the bundle rises. Higher temperature means more insertion loss, and a link that tested fine at handover can behave differently in a warm ceiling void under full load.

Standards bodies publish guidance on this, including on bundle sizes for remote powering. The practical habits are simple enough: do not build bundles bigger than they need to be, give powered runs some air where the route allows, think about where the cable passes through insulation or enclosed spaces, and use the category of cable the design actually calls for.

None of it shows up on the day of the install. It shows up two summers later.

13/10/2026

Sooner or later every cabling engineer gets asked which way to lean. Copper or fibre.

The usual answers are slogans. Fibre is the future. Copper is dying. Neither tells you much about where the work will be.

The fibre case is real. Inside AI data centres, AFL has described the increase in fibre as anything between 10 and 20 times a traditional configuration. And the work rewards precision: high fibre counts, MPO connectivity, very tight loss budgets.

The copper case is quieter, but just as solid. Wi-Fi 7 access points need multi-gigabit uplinks and more power, which is why Cat6A is treated as the practical minimum on new wireless work. PoE can now deliver up to 90W. More power in a bundle means more heat and less tolerance for poor terminations.

So the better question is not which medium wins. It is which skills stay scarce. Testing and certification. Working in live, demanding environments. And the range to move between both on the same project.

The full article covers how to decide from where you are now. Link in the comments. 👇

08/10/2026

If your first live data centre job is coming up, the technical side is probably the part you need to worry about least.

What operators notice in the first week is everything around it.

Whether you read the method statement before the day, or in the hall. Whether you turned up early enough for induction and access, which always take longer than planned. Whether you unpacked outside. Whether the floor tiles went back before you left the area. And whether, when something did not match the plan, you stopped and asked instead of working around it.

None of it is complicated. All of it gets remembered.

A short checklist to save for the first week. 👇

06/10/2026

Most engineers learn their trade on construction sites. Nothing is running yet, and a mistake means rework.

A live data centre is a different job, even when the work looks identical. Same cable, same panels, same tests. The difference is that everything around you is already carrying customer traffic.

That changes what counts as a mistake.

Uptime Institute's 2025 outage analysis found that 58% of outages caused by human error came from staff not following procedures, up from 48% the year before. Its 2026 report found that cause still leads.

Which is why the engineers operators trust most are not always the fastest. They are the ones who work inside the method statement, stay within the permit, keep the hall clean, and stop and ask when what they find does not match the plan.

Most removals from live sites have nothing to do with technical ability. They come down to scope, access and housekeeping, and to not reporting a mistake straight away.

We have put together a practical guide to working on a live site, from permits to the first week. Link in the comments. 👇

At iCobus, our project delivery capability is backed by decades of experience across the telecommunications sector.With ...
01/10/2026

At iCobus, our project delivery capability is backed by decades of experience across the telecommunications sector.

With a career spanning more than 35 years, Graham Robertson has delivered major telecommunications and infrastructure projects across Europe and around the world.

As Project Manager, Graham applies that experience to planning, coordinating and managing delivery, with a strong understanding of the demands involved in complex telecommunications projects.

His international project background adds further strength to the specialist knowledge and delivery capability within iCobus.

Address

165 The Broadway
London
SW191NE

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Telephone

+442085440944

Alerts

Be the first to know and let us send you an email when iCobus: ICT, Telecoms & Cabling posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to iCobus: ICT, Telecoms & Cabling:

Shortcuts

Share

Nearby computer & electronics services