897 charging sessions. 126 MWh delivered.
Twenty-tonne electric excavators on the UK's flagship infrastructure project. No grid connection. No diesel generator.
Lower Thames Crossing wants around 130 zero-emission machines working by 2028. The plant is solved. The charging isn't.
Since January, Allye MAX500s have charged 20-tonne electric excavators on the Bouygues Murphy JV site. Volvo, SANY and LiuGong machines, topped up at 240kW DC between shifts, working alongside GeoPura’s green hydrogen.
No grid connection. No diesel generator.
Diesel is muscle memory. The bowser turns up, the tank fills, nobody thinks about it. Electric plant asks a site team to plan energy the way they plan concrete. That is a habit change, not an engineering one.
So we’ve logged everything. Every session, every fault, every workaround, every question asked on the ground. Nine months of it.
This spring, government named energy infrastructure as one of four sectors where public money should back British industry. In the minister’s words, “it matters where things are made and who makes them.”
A British road, paid for by British taxpayers, partly charged by batteries that first drove on British roads.
So here’s the question for the next 120 machines: will the energy behind them be built here, or shipped in?
Congratulations to the Lower Thames Crossing and BOUYGUES UK and Murphy JV teams. Pathfinder projects are hard, and this one is working.